Inclusive Growth through Decent Work in the Great Rift Valley - Final Evaluation

eval_number:
2892
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2892
location:
country:
Kenya
region:
Africa

eval_title:
Inclusive Growth through Decent Work in the Great Rift Valley - Final Evaluation
recommendations:
date:
2024-07-09 00:00:00.0
themes:
theme:
Constituents
category:
Government - capacity building

action_plan:
During the development of the project's new phase, the technical people and leadership of the governments both national and county governments was done. The recommendations to engage the county secretaries from the three counties as focal points will be considered, however noting that the governors have also appointed their Ministers as focal points and so the project acknowledges importance of strengthening the partnership through relevant focal offices
management_response:
Completed
progress:
Achieved
admin_units:
CO-Dar es Salaam
title:
7. There is need to involve the top echelons of the county governments including the governors and county assemblies. Stakeholders consulted during the evaluation indicated that the county secretary’s office would serve better as the focal point at county level, than the present arrangement. This should be explored further during the design of Phase 2. County Assemblies play the critical role in the county planning and budgeting approval processes; and thus, where there is buy-in into the PPDP interventions from them, this will ease release of counties’ counterpart funding. The dialogue platforms initiated through Outcome 3, where duty bearers and right holders meet were reported to have significantly contributed to enhanced service delivery in Raplands and Suswa.