Support to "Sustainable Rural Infrastructure Development Services for Poverty Reduction in the Asia Pacific Region" (Asist AP)- Final Evaluation

eval_number:
865
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/865
lessons_learned:
themes:
theme:
Programme implementation
category:
Organizational issues

comments:
N/A
challenges:
N/A
success:
N/A
context:
N/A
description:
The management capacity has been inadequate due to shortage of funds and its work can be characterised as fire fighting and keeping the programme afloat and providing as much services as possible. It has not always been possible to make the right priorities and to provide services required and some countries have, accordingly, been given less attention than originally envisaged. This is not sustainable in the long-term as a programme of this nature requires: adequate resources in order not to spread too thinly across the member countries; to have its staff in the field to a large extent, not only to accommodate the immediate needs of the stakeholders, but also to be 'on the ground' for stakeholder dialogues on further initiatives. Moreover it needs a flexible strategy over a longer period of support to ensure methods and approaches are sustained in the member countries. This requires more substantial funding, which leads over to the next lesson learned.
administrative_issues:
N/A
url:
https://webapps.ilo.org/ievaldiscovery/lessons/157075

location:
country:
Asia and the Pacific - regional
region:
Asia and the Pacific

eval_title:
Support to "Sustainable Rural Infrastructure Development Services for Poverty Reduction in the Asia Pacific Region" (Asist AP)- Final Evaluation
Skip to top