Back to index
Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation
- eval_number:
- 967
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/967
- lessons_learned:
- themes:
- theme:
- Planning and programme design
- category:
- Organizational issues
- comments:
- N/A
- challenges:
- N/A
- success:
- N/A
- context:
- N/A
- description:
- The original eighteen-month project duration was much too short. This was apparent at the time of the MTR when a six-month extension was agreed. With additional funding and time extended to 3 years and 7 months it was possible to achieve all the main outputs. It is important that realistic estimates of time be included in future projects.
- administrative_issues:
- N/A
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/167765
- location:
- country:
- East Timor
- region:
- Asia and the Pacific
- eval_title:
- Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation
Skip to top