Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation

eval_number:
967
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/967
lessons_learned:
themes:
theme:
Planning and programme design
category:
Organizational issues

comments:
N/A
challenges:
N/A
success:
N/A
context:
N/A
description:
The original eighteen-month project duration was much too short. This was apparent at the time of the MTR when a six-month extension was agreed. With additional funding and time extended to 3 years and 7 months it was possible to achieve all the main outputs. It is important that realistic estimates of time be included in future projects.
administrative_issues:
N/A
url:
https://webapps.ilo.org/ievaldiscovery/lessons/167765

location:
country:
East Timor
region:
Asia and the Pacific

eval_title:
Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation