Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation
- eval_number:
- 967
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/967
- lessons_learned:
- themes:
- theme:
- Rural economy
- category:
- Economic and social development
- comments:
- N/A
- challenges:
- N/A
- success:
- N/A
- context:
- N/A
- description:
- A further lesson learnt was that assumptions on the availability of local compaction equipment (vibrating rollers) for hire were overly optimistic. The project bought some and hired others. Breakdowns were frequent and, as the rollers were a key piece of equipment, this delayed work on construction. In future projects adequate numbers of rollers must be bought at the start of the project and there must be spare machines to take over when there is a breakdown. Spare parts must also be purchased.
- administrative_issues:
- N/A
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/167770
- location:
- country:
- East Timor
- region:
- Asia and the Pacific
- eval_title:
- Investment budget execution support for rural infrastructure development and employment generation (TIM works) Norwegian Contribution - Final Evaluation