Improving social protection and promoting employment - Final Evaluation

eval_number:
1690
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/1690
lessons_learned:
themes:
theme:
Risk management
category:
Organizational issues

comments:
N/A
challenges:
N/A
success:
N/A
context:
N/A
description:
Time lost during the first months of the project due to internal (slowly-implemented activities) and external causes (political unrest in Honduras and Burkina Faso) was critical to understand the short time devoted to National Policy Dialogue Forums and workshops to discuss results of the project. In other words, time is gold and losing too much time during the first stages may complicate the implementation of later activities, perhaps the most important of the project. Future initiatives should be aware of a series of issues before planning the calendar of implementation: the likelihood that something will go wrong (risk assessment), the time allocated to administrative issues (personnel and hiring of consultant) and the level of flexibility the project management guidelines offer in case any variation is required.
administrative_issues:
N/A
url:
https://webapps.ilo.org/ievaldiscovery/lessons/189815