Resource management
category:
Organizational issues

comments:
Targeted users / Beneficiaries ILO and potential donors
challenges:
The challenge is to find a balance between implementation needs and availability of financial resources. There is a need to better match the scope of activities with resources provided. While the concept of the project was well defined, the ambitious objectives were not matched with sufficient human resources.
success:
N/A
context:
The shortage of staff in the project office and in the field required the project to re-allocate planned international consultancy man-days to fulfill the tasks of a Technical Officer and call on the support of National Project Officers of the GMS TRIANGLE project and the ILO Country Offices. This shows that the initial staff allocation was insufficient to timely implement all planned activities
description:
Sufficient staff resources need to be allocated in order to facilitate project implementation.
administrative_issues:
The project team initially coped with the heavy workload in calling on external resources before adjusting the budget to allow the recruitment of a Technical Officer.
url:
https://webapps.ilo.org/ievaldiscovery/lessons/192687

location:
country:
Asia and the Pacific - regional
region:
Asia and the Pacific

eval_title:
Tripartite action to protect migrants from labour exploitation (ASEAN TRIANGLE) - Midterm evaluation
Skip to top