Irish Aid Phase II: Testing methodologies to support informal economy workers and small producers to combat hazardous child labour in their own sectors - Final Evaluation
- eval_number:
- 2259
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/2259
- lessons_learned:
- themes:
- theme:
- Planning and programme design
- category:
- Organizational issues
- comments:
- ILO/IPEC/FPRW
- challenges:
- Time available for project execution is insufficient. Parners are not used to use formats or ILO Offices (regional, central) are slow to efficiently give feed back and collaboration for the formulation of project documents.
- success:
- Local partners gained some experience in drafting, more accurate planning
- context:
- The preparation of the partners' Action Programmes took almost one year before approval.
- description:
- Limited project duration does not allow enough time to appropriately deliver project activities in a consequential manner to achieve greater impact
- administrative_issues:
- Concerning the long hesitancies and re-formulations of Actions Programmes, ILO could provide, in the future, an online assistance to applicants during the timeframe of one month, when during Action Programmes design
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/205324
- location:
- country:
- Inter-Regional
- region:
- Inter-Regional
- eval_title:
- Irish Aid Phase II: Testing methodologies to support informal economy workers and small producers to combat hazardous child labour in their own sectors - Final Evaluation