Roads for Development (R4D) Phase II - Final evaluation
- eval_number:
- 2695
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/2695
- lessons_learned:
- themes:
- theme:
- Capacity building
- category:
- Organizational issues
- comments:
- R4D-SP Staff, MPW, Municipalities
- challenges:
- Promotes an unsustainable model of work.
- success:
- Opportunity to rectify the issue and provide more targeted training and support with associated tools (manuals, guidelines etc.)
- context:
- The focus of the program is on capacity development and institutional strengthening. However, there is a risk that the “embedded” nature of the program leads to possible overlaps with regards to roles and responsibilities and levels of influence over work and decision-making.Capacity constraints are evident at the central and municipal level. Lack of operating budgets means that R4D-SP advisers take on more “high-profile” roles to supervise and complete work.
- description:
- The embedded model, while identified as a good practice runs the risk of implementing “capacity substitution” effects. It is important to ensure all technical advisers and staff have a direct counterpart (individual or work unit) and have a clear capacity development plan and workplan, including a transition plan with strategies on how to effectively handover skills and knowledge in defined timeframes.
- administrative_issues:
- Require clear guidance and briefings from management how to implement capacity and institutional work.
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/212447
- location:
- country:
- East Timor
- region:
- Asia and the Pacific
- eval_title:
- Roads for Development (R4D) Phase II - Final evaluation