- comments:
- Project management teams
- challenges:
- Not taking into consideration recommendations made by external evaluators diminishes the value of an evaluation and does not allow making progress
- success:
- n/a
- context:
- The evaluation of the 2015-2017 evaluation made 12 recommendations, of which several already were repeat recommendations from previous evaluations; 4 have not been taken into consideration.
- description:
- Independent evaluations are not sufficiently taken into consideration
Besides assessing the progress of projects, an important part of an evaluation is to formulate recommendations which aim to correct and/or improve weaknesses observed by the evaluators. While recommendations can be accommodated when they are deemed to be somewhat unrealistic, they should not be ignored
- administrative_issues:
- Resources are often not necessary to follow recommendations but require the willingness to learn from independent consultants.
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/231873
- location:
- country:
- Asia and the Pacific - regional
- region:
- Asia and the Pacific
- eval_title:
- 2018-2020 ILO/Korea Partnership Programme funded projects in ASEAN, Thailand, Cambodia, Lao PDR, Myanmar and Vietnam - Final evaluation
Skip to top