Reducing vulnerability in Lao PDR: Advancing social protection and labour rights and entitlements in the coffee and tea sectors of Lao PDR - Final independent evaluation
- eval_number:
- 3413
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/3413
- lessons_learned:
- themes:
- theme:
- Programme implementation
- category:
- Organizational issues
- comments:
- Project implementers, relevant government agencies (Lao Social Security Organization)
- challenges:
- Limitations in government available resources may affect in the sustainability of interventions
- success:
- Continued commitment contributes to ownership.
- context:
- Before starting a project, it is important to assess the long-term commitment of local stakeholders.
- description:
- 1. Consider long-term interventions when working on social security and occupational safety and health issues. Duration of interventions: Increasing the coverage of social security systems and occupational safety and health practices is a long-term commitment that requires continuous action and investment by government agencies.
- administrative_issues:
- Prepare in advance and monitor the implementation of an exit plan for the project.
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/2335897
- location:
- country:
- Lao People's Democratic Republic
- region:
- Asia and the Pacific
- eval_title:
- Reducing vulnerability in Lao PDR: Advancing social protection and labour rights and entitlements in the coffee and tea sectors of Lao PDR - Final independent evaluation