Egypt Youth Employment: Economic Empowerment under FORSA programme

eval_number:
2343352
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2343352
lessons_learned:
themes:
theme:
Programme implementation
category:
Organizational issues

comments:
Stakeholders and beneficiaries involved in the project
challenges:
Delays in the project due to delays in the national programme
success:
Flexibility in budget allocation in the project to take over some of the responsibilities of the government (provision of assets) to mitigate delays.
context:
The EYE:FORSA project aimed to support the implementation of the government’s Forsa programme in two governorates. However, as the national Forsa programme was heavily delayed, the project could not ensure that project activities built on support (assets) provided by the government. This caused delays in the project and barriers to effectiveness, that were outside the project’s control.
description:
Project implementation may be significantly impacted by the quality and timeliness of parallel national efforts If a project comprises technical assistance to a national programme, the project may be affected by challenges and delays outside its control if such issues arise in the national programme.
administrative_issues:
Projects depending largely on national efforts should have risk mitigation and “plan B’s” in case the national component is not delivered as planned.
url:
https://webapps.ilo.org/ievaldiscovery/lessons/2343493

location:
country:
Egypt
region:
Africa

eval_title:
Egypt Youth Employment: Economic Empowerment under FORSA programme
Skip to top