Promoting Decent Work for Women in Türkiye - Final Evaluation

eval_number:
2974
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2974
lessons_learned:
themes:
theme:
Programme implementation
category:
Organizational issues

comments:
Targeted users and beneficiaries include the project’s tripartite constituents and civil society organizations. By involving these stakeholders early on, the project not only secures funding but also ensures that all parties are aligned, and can contribute to securing financial sustainability.
challenges:
One of the challenges identified was the difficulty or omission in securing diverse funding sources early on, particularly in complex or evolving political and economic environments, based on comprehensive stakeholder mapping allowing to identify diverse sources of funding.
success:
Early and comprehensive stakeholder mapping and engagement can uncover emerging opportunities and support the development of a more robust funding strategy. By actively seeking coordination with other ILO projects, relevant organizations, and public sector stakeholders, the project can strengthen its financial sustainability and reduce the risks associated with over-reliance on a single funding stream. This approach enhances flexibility and ensures continued support for the project’s long-term success.
context:
The approach is most effective in environments where initial buy-in from key stakeholders is achieved, and there is an existing willingness to collaborate with various actors, such as governments, donors, and private sector organizations. Additionally, a strong tripartite framework and open social dialogue channels are essential for successful engagement and identifying funding opportunities.
description:
A key lesson learned is the importance of securing funding from multiple donors, leveraging both planned and emerging funding opportunities throughout the project’s design and implementation. This approach not only enhances the project’s financial sustainability and flexibility but also ensures the project’s alignment with broader development initiatives, improving its long-term viability.
administrative_issues:
Coordinating multiple funding streams can present administrative challenges, requiring sufficient staffing, flexibility, and resources to effectively monitor and manage interventions funded by different donors.
url:
https://webapps.ilo.org/ievaldiscovery/lessons/2348644

location:
country:
Türkiye
region:
Europe and Central Asia

eval_title:
Promoting Decent Work for Women in Türkiye - Final Evaluation