Promoting Decent Work for Women in Türkiye - Midterm Evaluation

eval_number:
2973
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2973
lessons_learned:
themes:
theme:
Planning and programme design
category:
Organizational issues

comments:
Implementing partners of the project, particularly ILO and ISKUR
challenges:
The internal structural change taken place in the partner organization which caused departmental changes inside, the need for getting an approval from higher level in regard to content of the trainings but not least infamous COVID-19 created challenges on the implementation of the project.
success:
Since there has been a successful collaboration between the partners for some period of time and they have gained quite experience in collaborating, and they have all committed for the achieving the objectives of the project,. Therefore, defining roles, responsibilities, expectations of each side in the initial stages of the project will enhance efficiency and their smooth collaboration will make the project meet its ends in time
context:
Beyond COVID-19, there were several delays while initiating and implementing activities. Even though all interventions, activities under Outcome 1 were planned together between the partners and there were some delays along the way.
description:
Defining and agreeing on roles and responsibilities between partners/stakeholders in the initial stages of the project is essential for enhancing the efficiency of the outcomes: The expectations and responsibilities of each stakeholder in the project needs to be laid out openly in this discussion, in order to make sure the next steps of the program can be implemented with ease and the learnings of this phase of the program can be used constructively in developing the partnership between organizations involved in the project. Beyond the document that elaborating the tasks and responsibilities, elaboration of risk and mitigation strategies in the program design process will enhance efficiency. All these components and the practice of innovative methods and tools to inform and involve stakeholders will ensure their commitment and support.
administrative_issues:
Specific assistance needs to be given to the stakeholders for developing their institutional capacity such as the project management, designing and implementing each stage together in a more coherent way.
url:
https://webapps.ilo.org/ievaldiscovery/lessons/237339

location:
country:
Türkiye
region:
Europe and Central Asia

eval_title:
Promoting Decent Work for Women in Türkiye - Midterm Evaluation