Independent evaluation of the first phase of the ILO global flagship programme on building social protection floors for all (2016 – 2020)

eval_number:
3362
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/3362
lessons_learned:
themes:
theme:
Monitoring and evaluation
category:
Organizational issues

comments:
Target users: SOCPRO, Flagship projects. Target beneficiaries: SOCPRO, Flagship projects, donors.
challenges:
Lack of systematic mainstreaming of the Results Monitoring Tool in project documents.
success:
Strong expectations from Programme management and donors to implement the Results Monitoring Tool.
context:
Gaps in the uptake and implementation of the Results Monitoring Tool.
description:
Systematizing the use of a Results Monitoring Tool (RMT) requires devising and implementing a multi-faceted approach that goes beyond the improvement of an IT platform and delivery of trainings. It also needs to consider mainstreaming the tool in (i) PRODOCs and therefore establishing a minimum level of consistency between the project results framework and Project Monitoring Plan, and the RMT; (ii) job descriptions so as to make explicit the responsibility to ensure that the RMT is kept up to date; (iii) the work plans of the offices; (iv) and in resource mobilization and advocacy efforts, including with development of joint branding and communication tools, success stories, champions, etc.
administrative_issues:
n/a
url:
https://webapps.ilo.org/ievaldiscovery/lessons/247616

location:
country:
Inter-Regional
region:
Inter-Regional

eval_title:
Independent evaluation of the first phase of the ILO global flagship programme on building social protection floors for all (2016 – 2020)