More and Quality jobs are created through better policies and frameworks and strengthened labour market information systems - RBSA independent evaluation
- eval_number:
- 3076
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/3076
- lessons_learned:
- themes:
- theme:
- Programme sustainability
- category:
- Organizational issues
- comments:
- ILO Liaison Office, donors, CSOs
- challenges:
- N/A
- success:
- N/A
- context:
- The delay in commencement and lack of flexibility in extending the end date of the project resulted in construction and training activities taking place during the wet season. This caused inefficiencies including loss of supplies (cement), a longer time taken to complete works and the need to purchase supplies from Thailand. Some of these additional costs were born by contractors who received negative profit.
- description:
- The ILO should consider carefully the amount of contingency funds to be included in the sub-contracts for community contractors to ensure community contractors are not out of pocket.
- administrative_issues:
- N/A
- url:
- https://webapps.ilo.org/ievaldiscovery/lessons/250138
- location:
- country:
- Myanmar
- region:
- Asia and the Pacific
- eval_title:
- More and Quality jobs are created through better policies and frameworks and strengthened labour market information systems - RBSA independent evaluation