lessons_learned:
themes:
theme:
Planning and programme design
category:
Organizational issues

comments:
ILO Hqs, Project management and staff
challenges:
-
success:
-
context:
This project has no common LFA, or TOC, the reason for which may be the emergency nature of the project, which was also mentioned by the Mid term evaluation.
description:
In order to be perceived as ONE project/programme, not several projects put together, all ILO projects, even these large multi-country and inter-regional interventions, need to have common outcomes (but the outputs/sub-outputs can differ depending on the country context).
administrative_issues:
This is related to design – more efforts should be made to create common grounds as the project worked in one single sector (the garments).
url:
https://webapps.ilo.org/ievaldiscovery/lessons/253796

location:
country:
Madagascar
region:
Africa

country:
Indonesia
region:
Asia and the Pacific

country:
Inter-Regional
region:
Inter-Regional

country:
Bangladesh
region:
Asia and the Pacific

country:
Ethiopia
region:
Africa

country:
Lao People's Democratic Republic
region:
Asia and the Pacific

country:
Cambodia
region:
Asia and the Pacific

country:
Viet Nam
region:
Asia and the Pacific

eval_title:
Protecting garment sector workers: occupational safety and health and income support in response to the COVID-19 pandemic - Final evaluation
Skip to top