Employment Intensive Infrastructure Program (EIIP) - Midterm Evaluation

eval_number:
2942
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2942
location:
country:
Lebanon
region:
Arab States

eval_title:
Employment Intensive Infrastructure Program (EIIP) - Midterm Evaluation
recommendations:
date:
2019-03-06 00:00:00.0
themes:
theme:
Organizational issues
category:
Resource management

comments:
KfW did not support the proposal to include a specific study on cost comparison between Labour Based Tchnology and Conventional methods in Phase III.
action_plan:
The revised project selection criteria will be introduced in the Project Management Committee Meeting including the emphasis on labour intensity as a key selection criteria. This will allow identification and selection of projects more suitable to labour-based implementation. The project team will continue to produce cost comparison for various activities, to provide further arguments for selection of appropriate projects.
management_response:
Partially Completed
progress:
Partially achieved
admin_units:
RO-Arab States/DWT-Beirut
title:
Using current implementation experiences, the ILO and UNDP should tighten cost calculations for infrastructure activities (road and sidewalks and environmental works). This will provide the basis for negotiating with the Government on the need for inclusion of some environmental works activities such as forestry and road maintenance on the percentage of the budget which must be allocated to labour (No resource implications. Low priority).
project_symbols:
LBN/16/03/DEU
url:
https://webapps.ilo.org/ievaldiscovery/recommendations/13032
information_source:
Regional Office