Enhance the resilience and self-reliance of crisis-affected rural communities (...) - Final evaluation

eval_number:
2542
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2542
location:
country:
Yemen
region:
Arab States

eval_title:
Enhance the resilience and self-reliance of crisis-affected rural communities (...) - Final evaluation
recommendations:
date:
2020-07-23 00:00:00.0
themes:
theme:
Organizational issues
category:
Planning and programme design

action_plan:
This is part of the standard operating procedures.
management_response:
Completed
progress:
Achieved
admin_units:
RO-Arab States/DWT-Beirut
title:
Include extra time for government approvals in project timelines. Better planning of logistics, given there is more interest from the government in Aden to avoid delays in implementation, requires planning periods longer than one month. As financial support is coordinated through ILO ROAS for internal clearance, it would be beneficial for the ILO project team to plan activities at least two months in advance. This will also increase the likelihood of obtaining approval from local authorities.
project_symbols:
YEM/15/01/UND
url:
https://webapps.ilo.org/ievaldiscovery/recommendations/13636