Implementation of the Agreement concerning additional employment injury benefits to the victims of the Ali Enterprises fire and strengthening... - Final evaluation
- eval_number:
- 2846
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/2846
- location:
- country:
- Pakistan
- region:
- Asia and the Pacific
- eval_title:
- Implementation of the Agreement concerning additional employment injury benefits to the victims of the Ali Enterprises fire and strengthening... - Final evaluation
- recommendations:
- date:
- 2021-08-19 00:00:00.0
- themes:
- theme:
- Organizational issues
- category:
- Planning and programme design
- comments:
- SESSI has a permanent governance structure, the SESSI Board and which is officially provided for under the SESS Act and with some overlap in membership. The OC is by notification.
Should the partners wish, the OC can continue for some time as may be deemed relevant.
- action_plan:
- The Oversight Committee was considered a temporary structure and very specific to the Baldia Arrangement. The role and possible continuation of this forum is part of overall consideration for the long-term sustainability of the Baldia Arrangement.
which eventually may get absorbed into the permanent structure, the SESSI Board and which is officially provided for under the SESS Act
Should the partners wish, the OC can continue for some time as may be deemed relevant.
- management_response:
- Action not yet taken
- progress:
- No implementation
- admin_units:
- CO-Islamabad
- title:
- The ILO and SESSI should consider options to formalise the OC as a means for technical oversight and strategic input, not only for the remaining 12-momths but as a model for other disasters and events that involve SESSI input
- project_symbols:
- PAK/16/06/DEU