Go to ILO main website
Back to index

International labour and environmental standards application in Pakistan's SMEs (ILES) - Midterm Evaluation

eval_number:
2607
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/2607
location:
country:
Pakistan
region:
Asia and the Pacific

eval_title:
International labour and environmental standards application in Pakistan's SMEs (ILES) - Midterm Evaluation
recommendations:
date:
2022-08-15 00:00:00.0
themes:
theme:
Organizational issues
category:
Programme implementation

action_plan:
The ILES project and Better Work programme hold a technical discussion on the partnership to synergy the support in Karachi on 27th August 2022. At the meeting, it's agreed that ILES project will take the lead on the legislation and policy development support with contribution from the Better Work. The Better Work programme will focus on enterprise support. The work on Freedom of Association and Collective Bargaining is on-going. The TOR on working group is developed and its composition was agreed with the MoOP&HRD on 10th Aug. The implementation plan is endorsed by the government. The first mission of the consultant will take place in October 2022 to collect additional missing data and information to fill knowledge gaps with respect to union registration, recognition, collective bargaining and mandated worker representation procedures. The support is being provided to Federal government on developing its 2nd national OSH profile. The support is also being provided to provinces on provincial OSH programmes. Training of labour inspectors are being mobilized to support the government of Sindh province.
management_response:
Partially Completed
progress:
Partially achieved
admin_units:
CO-Islamabad
title:
In consultation with ILO Country Office and considering possible arrival of Better Work Pakistan, continue to narrow the focus of policy/capacity building interventions in remaining implementation period. • Maintain strong focus on Sindh province. Work in other geographic areas should be strongly justified • Strengthen linkages between policy, capacity building and enterprise work, for example by reinforcing cross-cutting OSH linkages. • Follow through on studies: Non-standard forms of employment, FOACB and LDR .
project_symbols:
PAK/16/03/EUR
url:
https://webapps.ilo.org/ievaldiscovery/recommendations/14871
information_source:
Country Office

Skip to top