Employment through Labour Intensive Infrastructure in Jordan - Cluster evaluation

eval_number:
3005
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/3005
location:
country:
Jordan
region:
Arab States

eval_title:
Employment through Labour Intensive Infrastructure in Jordan - Cluster evaluation
recommendations:
date:
2021-12-13 00:00:00.0
themes:
theme:
Organizational issues
category:
Planning and programme design

comments:
Delays to the confirmation of budget and duration could delay the start of Phase VI. The impact of this delayed start have been discussed with KfW and ROAS
action_plan:
The project has held preliminary discussions with current and potential national partners on the concept of Phase VI. A KfW/ILO workshop on 6 September broadly endorsed the Concept Note. More detailed discussions will continue with partners at operational and Minister/SG level and the project team, and the project designed in detail with KfW once the budget and duration are known.
management_response:
Partially Completed
progress:
Partially achieved
admin_units:
RO-Arab States/DWT-Beirut
title:
The programme should commence immediate planning for an extension into Phase VI. This will involve coordination with KfW and government authorities at the central and municipal level to discuss and agree on the strategic intent and focus and overall mix of work priorities going forward.
project_symbols:
JOR/18/05/DEU
url:
https://webapps.ilo.org/ievaldiscovery/recommendations/15235
information_source:
Country Office