Back to index
Integrated Programme on Fair Recruitment (FAIR) - Phase II - Global and Hong Kong components - Final evaluation
- eval_number:
- 3188
- eval_url:
- https://webapps.ilo.org/ievaldiscovery/eval/3188
- location:
- country:
- Inter-Regional
- region:
- Inter-Regional
- country:
- Nepal
- region:
- Asia and the Pacific
- country:
- China
- region:
- Asia and the Pacific
- country:
- Jordan
- region:
- Arab States
- country:
- Tunisia
- region:
- Africa
- country:
- Philippines
- region:
- Asia and the Pacific
- eval_title:
- Integrated Programme on Fair Recruitment (FAIR) - Phase II - Global and Hong Kong components - Final evaluation
- recommendations:
- date:
- 2022-09-22 00:00:00.0
- themes:
- theme:
- Organizational issues
- category:
- Planning and programme design
- comments:
- Over its first two phases the FAIR project has collaborated extensively with other ILO projects, as observed in the MTR. This collaboration takes place through joint activities at country and global levels, cost-sharing of staff (country and global), and through the design of the project which is jointly implemented by 2 ILO branches/departments. Projects with which FAIR cost-shared activities and staff include joint-UN projects such as THAMM (IOM, GIZ, ILO), SAMM (ILO, IOM, UNODC, UNHCR), as well as regional projects (FCDO-funded WIF) and the global level EU funded project REFRAME. FAIR II supported global level symposium on FR, jointly with IOM and IHRB.
- action_plan:
- Going forward, collaboration with IOM for FAIR III is framed around an ILO-IOM Memorandum of Understanding and a joint workplan, in which fair recruitment has been selected as a priority area for collaboration with a focus on research, awareness raising and capacity building. The third phase of FAIR is deliberately built around cost-sharing of resources and has been set up as a multilateral donor (“MUL”) project, with a co-contribution from Italy of US900,000, to which an additional USD532,235 of ILO RB funds are added. Furthermore, there are no less than 10 ILO programmes (Accelerator lab 8.7, BRMM I and BRMM II, FAIRWAY, THAMM, SAMM, JLMP, JLMP priority, JLMP Action, FMM II, AGRIDOM), involved in cost-sharing of project outcomes.
- management_response:
- Completed
- progress:
- Achieved
- admin_units:
- FUNDAMENTALS
- title:
- For ILO HQ Administration: To develop a resource-mobilization and cooperation strategy with other ILO and UN projects including the IOM projects in the area of fair recruitment in the target countries to avoid duplication, maximize impact and ensure the accountability of the Project’s results.