Addressing the Worst Forms of Child Labour in Jordan - Final evaluation

eval_number:
3483
eval_url:
https://webapps.ilo.org/ievaldiscovery/eval/3483
location:
country:
Jordan
region:
Arab States

eval_title:
Addressing the Worst Forms of Child Labour in Jordan - Final evaluation
recommendations:
date:
2022-12-02 00:00:00.0
themes:
theme:
Organizational issues
category:
Programme implementation

action_plan:
ROAS will strengthen coordination with ILO Programme Coordination Office in Jordan to ensure timely and adequate backstopping of delivery of DC projects in Jordan.
management_response:
Completed
progress:
Partially achieved
admin_units:
RO-Arab States/DWT-Beirut
title:
3. Ensure that projects receive adequate, timely, and responsive administrative support Administrative support provided to projects should be timely, responsive and adequate to ensure a smooth implementation process, and avoid unnecessary delays that take away from the effectiveness and efficiency of a project. Internal policies and processes within the ILO should ensure full administrative support for projects, including timely recruitment of the project team and timely responsiveness to any request for administrative support or approvals.
project_symbols:
JOR/20/52/NOR